  "schema_version": "pct-editorial-1.0",
  "id": "pct-2026-11-04-deal-aib-nebius",
  "section": "Deals",
  "publisher": "Peterson Compute Trading",
  "as_of_date": "2026-11-04",
  "headline": "AIB–Nebius: 50 MW contracted, financing and delivery still ahead",
  "dek": "A September colocation commitment shows why signed capacity, project funding and delivered GPU supply need separate records.",
  "story_type": "Original public-source deal analysis",
  "freshness": "Agreement announced September 30, 2026; October disclosures reviewed November 4. Not a new November 4 deal.",
  "editorial_word_count": 653,
  "parties": {
    "supplier": "AIB Data Centers",
    "customer": "Nebius",
    "legal_customer": "Nebius Inc. referenced in issuer risk disclosures; full executed agreement not inspected"
  },
  "deal": {
    "asset_class": "AI data-center colocation",
    "critical_it_capacity_mw": 50,
    "utility_capacity_mw": 65,
    "initial_term_years": 12,
    "gpu_model": null,
    "gpu_count": null,
    "current_executable_gpu_hour_price": null,
    "historical_presentation_calculation": {
      "source_id": "S4",
      "contract_value_input_usd": 1320000000,
      "derived_usd_per_critical_it_mw_year": 2200000,
      "formula": "1320000000 / 12 / 50",
      "classification": "Historical issuer-presentation input and arithmetic, not a spot quote or independently verified realized price"
    }
  },
  "facts": [
    {
      "id": "F1",
      "claim": "AIB announced a binding 50 MW critical-IT agreement on September 30; initial term 12 years; utility agreement 65 MW.",
      "source_ids": [
        "S1"
      ],
      "evidence_type": "issuer_reported_signed_agreement"
    },
    {
      "id": "F2",
      "claim": "October 7 funding plan used customer prepayments and potential debt and preferred equity.",
      "source_ids": [
        "S2"
      ],
      "evidence_type": "management_plan"
    },
    {
      "id": "F3",
      "claim": "October deck targets Q4 2027 halls and calls project financing incomplete; AIB supplies facilities, customers supply compute.",
      "source_ids": [
        "S3"
      ],
      "evidence_type": "issuer_presentation_target_and_status"
    },
    {
      "id": "F4",
      "claim": "September deck used a $1.32bn implied-rate input; October peer examples expressly do not imply AIB terms.",
      "source_ids": [
        "S4",
        "S3"
      ],
      "evidence_type": "historical_disclosure_with_later_comparability_caveat"
    },
    {
      "id": "F5",
      "claim": "Nebius announced a separate $3.5bn Citi facility October 22, without a stated AIB allocation.",
      "source_ids": [
        "S5"
      ],
      "evidence_type": "issuer_reported_financing"
    }
  ],
  "inferences": [
    {
      "id": "I1",
      "claim": "Do not convert colocation MW into GPU-hour inventory without hardware and delivery evidence.",
      "basis_fact_ids": [
        "F1",
        "F3"
      ],
      "label": "PCT analysis"
    },
    {
      "id": "I2",
      "claim": "Nebius corporate financing does not establish CLT1 project financing or AIB cash receipts.",
      "basis_fact_ids": [
        "F2",
        "F3",
        "F5"
      ],
      "label": "PCT analysis"
    },
    {
      "id": "I3",
      "claim": "September presentation arithmetic is not an executable GPU price; later wording alone does not establish an amended agreement.",
      "basis_fact_ids": [
        "F4"
      ],
      "label": "PCT analysis"
    }
  ],
  "classification": {
    "signed": "Company-announced binding colocation commitment; full contract not independently reviewed",
    "financing": "Project financing incomplete in cited October presentation; later corporate Citi facility is separate",
    "delivered": "Not established by cited sources; latest cited target Q4 2027",
    "spot_execution": "Not observed or established",
    "gpu_hour_pricing": "Unknown",
    "cash_collected": "Unknown",
    "execution_volume": null
  },
  "unknowns": [
    "Executed agreement text and exact signing date",
    "Final capital structure and completed project financing",
    "Prepayment amounts, receipt and escrow-release status",
    "Current contract value and detailed rent escalators/pass-throughs",
    "Construction completion and customer acceptance",
    "GPU models, counts, topology and deployment",
    "Utilization, realized revenue and spot execution",
    "Resale/assignment rights and complete termination provisions"
  ],
  "methodology": {
    "source_basis": "Public issuer releases and presentations; original synthesis, not republished reporting.",
    "verification_limit": "No interviews, account access, trade execution, independent operational measurement or full contract review. Negative claims are bounded to cited materials.",
    "source_history": "September and October presentations are preserved as separate vintages; no inference of contractual amendment from differences in wording.",
    "copyright": "No source images or substantial quotations reproduced; source facts paraphrased with links."
  },
  "sources": [
    {
      "id": "S1",
      "title": "AIB Data Centers Signs Contract with Nebius for AI Data Center Capacity",
      "publisher": "AIB Data Centers, SEC-hosted company release",
      "published_at": "2026-09-30",
      "url": "https://www.sec.gov/Archives/edgar/data/2070542/000121390026105865/ea030737801ex99-1.htm",
      "primary": true,
      "supports": "Announced binding agreement; capacity; term; utility-load support; expected funding.",
      "retrieved_at": "2026-11-04"
    },
    {
      "id": "S2",
      "title": "AIB Data Centers Issues CEO Letter Highlighting Recent Milestones and CLT1 Development Strategy",
      "publisher": "AIB Data Centers, SEC exhibit",
      "published_at": "2026-10-07",
      "url": "https://www.sec.gov/Archives/edgar/data/2070542/000121390026107421/ea030792301ex99-1.htm",
      "primary": true,
      "supports": "Customer funding, planned debt and preferred equity, and remaining execution priorities.",
      "retrieved_at": "2026-11-04"
    },
    {
      "id": "S3",
      "title": "AIB Data Centers October 2026 Investor Presentation",
      "publisher": "AIB Data Centers",
      "published_at": "2026-10",
      "date_precision": "month",
      "url": "https://www.aib.us/docs/AIB-Investor-Presentation-October-2026.pdf",
      "primary": true,
      "supports": "Pages 6, 8, 10 and 11: facility/compute distinction, delivery target, pricing caveat and incomplete financing.",
      "retrieved_at": "2026-11-04"
    },
    {
      "id": "S4",
      "title": "AIB Data Centers Q3 2026 Investor Presentation, furnished September 30",
      "publisher": "AIB Data Centers, SEC exhibit",
      "published_at": "2026-09-30",
      "url": "https://www.sec.gov/Archives/edgar/data/2070542/000121390026105249/ea030723301ex99-1.htm",
      "primary": true,
      "supports": "Page 4 historical implied-rate calculation; this is presentation evidence, not the complete contract.",
      "retrieved_at": "2026-11-04"
    },
    {
      "id": "S5",
      "title": "Nebius secures $3.5 billion financing facility with Citi",
      "publisher": "Nebius",
      "published_at": "2026-10-22",
      "url": "https://nebius.com/newsroom/nebius-secures-3-5-billion-financing-facility-with-citi",
      "primary": true,
      "supports": "Separate corporate facility, duration, initial interest margin and stated use of proceeds.",
      "retrieved_at": "2026-11-04"
    }
  ],
  "corrections": {
    "version": 1,
    "published_corrections": [],
    "policy": "Append dated corrections identifying the affected claim, old and new values, and supporting source. Preserve the prior vintage; do not silently relabel targets as delivery."
  },
  "license": {
    "original_analysis": "Original commissioned PCT text. Apply the edition’s authorized distribution license to original prose only.",
    "third_party_material": "Linked source materials remain subject to their publishers’ rights and terms; no license to third-party text or images is conferred.",
    "distribution_license": "Not independently assigned by this research draft."
  },
  "body": "AIB’s agreement with Nebius offers a useful test of how a compute-market ledger should record a large infrastructure commitment. On September 30, AIB announced a binding agreement covering 50 MW of critical IT capacity in the southeastern United States, over an initial 12-year term. The company said a 15-year electric-service agreement supported 65 MW of utility load. Those are different measurements of the project, not two quantities to add together. This is a November 4 review of an earlier transaction, rather than a newly signed deal. [September 30 announcement](https://www.sec.gov/Archives/edgar/data/2070542/000121390026105865/ea030737801ex99-1.htm)\n\nThe purchased product matters. AIB’s October presentation describes a facility business: the provider supplies the building, electrical infrastructure and cooling, while the customer installs and operates the servers and GPUs. The disclosed commitment therefore belongs in a colocation ledger. Converting it into accelerator-hours would require hardware, configuration, operating and service assumptions that the headline megawatt figure cannot supply. [October presentation, page 6](https://www.aib.us/docs/AIB-Investor-Presentation-October-2026.pdf)\n\nFunding is another separate record. In its October 7 shareholder letter, AIB described a plan combining customer prepayments with potential project-level debt and preferred equity. Management said it did not then anticipate needing corporate-level common equity for CLT1. That statement describes an intended capital structure, not proof that every funding source has closed. The same letter named securing project financing and advancing delivery among the next priorities. [October 7 shareholder letter](https://www.sec.gov/Archives/edgar/data/2070542/000121390026107421/ea030792301ex99-1.htm)\n\nThe October presentation makes the remaining work more explicit: project financing was incomplete, and two 25 MW halls were targeted for Q4 2027. A target should remain a target in the data. Recording these halls as available supply today would erase the construction and commissioning interval that a buyer still has to manage. [October presentation, pages 8 and 11](https://www.aib.us/docs/AIB-Investor-Presentation-October-2026.pdf)\n\nPricing also needs its original context. AIB’s September SEC presentation used $1.32 billion divided by 12 years and 50 MW in an implied-rate calculation. That arithmetic produces $2.2 million per critical-IT MW-year. The October deck instead presents other companies’ lease examples and explicitly warns that they do not establish AIB’s terms. This review does not interpret the change as a contract amendment or a withdrawal of the earlier figure. Neither presentation establishes a current executable GPU-hour price. [September presentation, page 4](https://www.sec.gov/Archives/edgar/data/2070542/000121390026105249/ea030723301ex99-1.htm) [October presentation, page 10](https://www.aib.us/docs/AIB-Investor-Presentation-October-2026.pdf)\n\nA more recent financing event provides context, but cannot close CLT1’s funding record by association. On October 22, Nebius announced a separate $3.5 billion senior secured Citi facility with a 364-day maturity, initially priced at Term SOFR plus 2.75 percentage points. Stated uses include data-center development, GPU procurement and general corporate purposes. The announcement does not allocate a disclosed amount to AIB. It establishes a financing agreement at Nebius, not a customer payment received by AIB or acceptance of either hall. [Nebius financing announcement](https://nebius.com/newsroom/nebius-secures-3-5-billion-financing-facility-with-citi)\n\nFor Peterson Compute Trading, the analytical lesson is to preserve several independent states: contract signed, financing committed, cash received, facility accepted, compute available and workload executed. A change in one state should not automatically update the others. A procurement agent should attach a source date to each transition and leave unsupported fields unknown. That approach makes a large deal useful for supply planning without allowing it to contaminate a spot-price series.\n\nThe next evidence to seek is specific: completed project-finance documentation, disclosed prepayment receipt or release, construction milestones, customer acceptance and actual service commencement. For downstream compute comparisons, the missing fields include accelerator model and count, usable cluster topology, service duration, commercial restrictions and the delivered price basis. No spot transaction, resale right, completed GPU deployment or workload execution is established by this review. Unknown execution volume should remain null, rather than becoming either zero or the entire contracted capacity.\n\nThe agreement is meaningful evidence that a buyer committed to future infrastructure. Its trading relevance lies in the conditional path from that commitment to usable supply. Keeping that path visible is more informative than compressing the deal into a dollar headline or treating a planned megawatt as inventory that can be sold today.",
  "content_type": "transaction_analysis",
  "title": "AIB–Nebius: 50 MW contracted, financing and delivery still ahead",
  "publication_date": "2026-11-04",
  "observation_date": "2026-11-04",
  "editorial_voice": "Deals Desk | AI-assisted, evidence-first",
  "license_status": "Private original PCT prose; public license undecided. External sources retain their own rights.",
  "public_url": null,
  "public_projection": {
    "version": "1.0.0",
    "date": "2026-11-10",
    "changes": [
      "Internal workspace artifact paths omitted where present. Historical license/status fields retain original provenance; current public reuse policy is stated separately."
    ],
    "rights": "PCT reserves rights in original editorial content; third-party rights retained. No general source-data reuse license."
  }
}